Major Performance
-
Korea Myeongdong Marina Seawall / DCM
-
Period
2014.08 ~ 2015.09
-
Client
Changwon-si, Gyeongsangnam-do
-
Location
Changwon-si, Gyeongsangnam-do, Republic of Korea
-
Explanation
Off-Shore DCM
(Long Pile) : 26,163M
(Short Pile) : 8,863M
-
Qatar Doha Metro Integrated Railways Project(Red Line South)/Shield Tunnel
-
Period
2014.07 ~ 2016.12
-
Client
Qatar Railways Company
-
Location
Doha, State of Qatar
-
Explanation
EPB, Length-10,864(M), Diameter-6,800(mm), Ground: Lime Stone, Midra shale
-
Korea Site B construction of Centum City / Underground Passage Work
-
Period
2014.06 ~ 2016.06
-
Client
Busan, Republic of Korea
-
Location
Centum Shinsegae Department Store
-
Explanation
Earthwork
-
Korea Jangmun Nature Gas Power Plant Underground Transmission Cable Tunnel/Shield Tunnel
-
Period
2014.06 ~ 2016.08
-
Client
SK E&C
-
Location
Paju, Gyeonggi-do, Republic of Korea
-
Explanation
Shield Tunnel
-
Myanmar Daewoo Amara Hotel Project
-
Period
2014.05 ~ 2015.12
-
Client
Daewoo E&C
-
Location
Yangon, Myanmar
-
Explanation
Earthwork, Bored Pile
-
Malaysia Cooling Water Intake System for Fast Track 3A Project in Manjung/Shield Tunnel
-
Period
2014.04 ~ 2016.08
-
Client
TNB (TENAGA NATIONAL BERHAD)
-
Location
Perak, Malaysia
-
Explanation
DCM, D-Wall, Steel Caisson, TBM Diameter 6,750(mm)