Major Performance

  • Singapore Downtown Line Stage 2 Contract 915 / Shield Tunnel

    • Period 2010.01 ~ 2015.07
    • Client LTA
    • Location Singapore
    • Explanation Slurry : Length - 4,634(M), Diameter - 6,650(mm)
      Ground : Bukit timah Granite, Complex Stratum
  • Korea Soyang River Dam Selective intake system Construction/ Headrace Tunnel and Intake Water Tower

    • Period 2010.01 ~ 2017.06
    • Client Korea Water Resources Corporation
    • Location Chuncheon Gangwon-do, Republic of Korea
    • Explanation Sectional area : (vertical hole : 275㎡, Tunnel 72㎡)
      Extended Length : (vertical hole : 46m, Tunnel : 70m)
      Rock Type : Soft / Hard rock
  • Korea Cheongra A28block RCD

    • Period 2009.12 ~ 2010.04
    • Client Hunghwa Co.
    • Location Incheon, Republic of Korea
    • Explanation D1500 40hole 36M
      D2000 129hole 32.8M
      Oscillator+BG+R.C.D
  • Cambodia The Construction of Pile Work and Earth Work of The Branch of POSCO E&C the # Star River Project

    • Period 2009.11 ~ 2010.11
    • Client Daesan Cambodia Co
    • Location Cambodia
    • Explanation Bored Pile
  • Singapore Marina Coastal Expressway CONTRACT 482 / DCM

    • Period 2009.08 ~ 2010.06
    • Client LTA
    • Location Singapore
    • Explanation DCM Length :
      Construction 172,369m
      improvement 428,164m
      (D=1,200mm, 2 drives)
  • Korea Seoul-Busan High Speed Railway 10-1

    • Period 2009.07 ~ 2014.04
    • Client Korea Rail Network Authority
    • Location Gyeongbuk, Republic of Korea
    • Explanation Sectional area : 122㎡
      Extended Length : 3,860m(Main Tunnel 3,810m, Open Cut Tunnel 50m)
      Rock Type : Hard Rock